Dewatered Construction of a Braced Excavation

Programvara

Version Notes:
FLAC 8.0

Level: Advanced
Runs in Demo: No

Write Up
Walk Through
Project Files
Konsulttjänster

A braced excavation is constructed in saturated ground. The construction stages, dewatering, excavation and braced support construction are simulated with FLAC. The purpose is to evaluate the deformation of the ground adjacent to the excavation and the performance of the wall and strut support. Three different material constitutive models are used to represent the soil behavior: Mohr-Coulomb, Cysoil, and PH models. The deformational response produced by these three models are compared.

Keywords:

  • Braced excavation
  • Saturated soil
  • Horizontal struts
  • Diaphram wall
  • support
  • Dewatering
  • Mohr-Coulomb model
  • Cysoil model
  • PH model
  • Plastic
  • Hardening
  • Construction sequence
  • Excavation
  • Settlement

Materials:

  • Clay
  • Sand
  • Soil
  • Water

Analyses:

  • Fluid Flow
  • Static
Senaste nytt
  • Operativ bergmekanik På ITASCA gillar vi en blandning av fältjobb och analyser. Vi erbjuder stöd inom operativ...
    Läs mer
  • Jennifer firar fem år med strategisk roll ...
    Läs mer
  • Axel tillbaka med nya perspektiv ...
    Läs mer

Kommande händelser
23 sep.
Getting Started with FLAC2D/FLAC3D
This training is an introduction to continuous modeling with FLAC2D and FLAC3D. At the end of the course, participants will master the ... Läs mer
14 okt.
Getting Started with 3DEC
Live Online Introductory Training Course. October 14-15, 2025... Läs mer
2 dec.
NEW TRAINING: Meshing in ITASCA Software
This introductory training course offers a comprehensive foundation in geotechnical modeling, enabling participants to identify various... Läs mer