A circular lined tunnel is constructed in saturated ground. The ground is dewatered during construction. The tunnel is supported by a temporary shotcrete liner, which is installed while the tunnel excavation is advanced. A final cast-in-place concrete liner is then constructed. The water level is then returned to the original level. The analysis determines the forces and moments that develop in the concrete liner when the water level is returned to the original level, and when the temporary shotcrete liner loses strength.

Keywords:

  • Circular
  • Tunnel
  • Saturated soil
  • Dewatering
  • shotcrete
  • concrete
  • liner

Materials:

  • Concrete
  • Soil
  • Water

Analyses:

  • Fluid Flow
  • Static
Latest News
  • WEBINAR: Solving Geothermal Challenges with XSite Numerical Modeling ITASCA Software and Baker Hughes are hosting a collaborative webinar to demonstrate how combining advanced...
    Read More
  • Newsletter October 2023 ...
    Read More
  • Newsletter August 2023 ...
    Read More

Upcoming Events
11 Aug
ITASCA Joins Caving 2026 as a Main Sponsor
We are pleased to announce that ITASCA will be participating as a Main Sponsor in Caving 2026, the leading international conference ded... Read More
15 Sept
ITASCA at EUROCK 2026: Advancing Innovation in Rock Engineering
ITASCA is pleased to announce its participation in EUROCK 2026 – ISRM Regional Symposium, taking place from 15–19 September 2026 in Sko... Read More
20 Sept
ITASCA to Participate in CouFrac 2026
ITASCA will be participating in CouFrac 2026, taking place from 20–23 September 2026 in Uppsala, Sweden. The conference brings together... Read More